Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Current Status | ||
---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | |||
Project Milestone-I | 150 | 20% | 09.05.2022 | 20% | 06.10.2022 | |
Project Milestone-II | 330 | 35% | 05.11.2022 Revised 14.04.2023 |
35% | 31.03.2023 | |
Project Milestone-III | 510 | 75% | 04.05.2023 Revised 06.03.2024 |
75% | 06.05.2024 | |
Schedule Completion | 730 | 100% | 10.12.2023 Revised 15.11.2024 |
91.84% |