Project Milestones

Project Milestones

Project Milestone Description (Days from Appointed Date) Planned Actual Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 150 20% 09.05.2022 20% 06.10.2022  
Project Milestone-II 330 35% 05.11.2022
Revised
14.04.2023
35% 31.03.2023
Project Milestone-III 510 75% 04.05.2023
Revised
06.03.2024
75% 06.05.2024
Schedule Completion 730 100% 10.12.2023
Revised  
15.11.2024
    91.84%