Project Name | Construction of Eight lane access-controlled Expressway from Km 217.500 to Km 254.430 of Vadodara Mumbai Expressway (Ena to Kim Section) in the State of Gujarat on Hybrid Annuity Mode under BharatmalaPariyojana (Phase -I, Package -VI). |
NH No. (New/old) | New |
---|
Scheme/Phase | BharatmalaPariyojna |
---|
Mode of Execution | HAM |
---|
No. of Lanes/Configuration | Eight Lane |
---|
Bid Project Cost | 2187 Cr. |
---|
No. Of Major Bridges | New MJB on MCW - 04 Nos. |
---|
No. Of Minor Bridges | New MNB on MCW-15 Nos. |
---|
No. of Culverts | Culverts-124 Nos. |
---|
No. of FO | 03 Nos. |
---|
No. of ROB | 01 Nos. |
---|
No. of VOP | 01 Nos. |
---|
No. of Underpasses | 42 Nos.(VUP-9,LVUP-15 ,SVUP-18) |
---|
No. of Interchange | 01 Nos. |
---|
Toll Plaza | 01 Nos. |
---|
Concessionaire Name | - GR ENA-KIM EXPRESSWAY PRIVATE LIMITED |
---|
Date of Letter of award(LOA) | 30.07.2020 |
---|
Appointed Date | 11.12.2021 |
---|
Construction Period (in Days) | 730 Days |
---|
Schedule Completion Date | 730 days from Appointed Date |
---|
Operation & Maintenance Period | 15 Years from the Commercial Operation Date |
---|
Independent Engineer | L.N Malviya Infra Projects Pvt. Ltd. |
---|
Authority Name | National Highways Authority of India, PIU-Surat |
---|
Independent Engineer Mobilization Date | 02.02.2021 |
---|